Trying to keep people up to date with our build is nearly impossible. Hopefully this blog might make things a little easier...

Thursday, 18 August 2016

Verandah

Jay (with very little help from me) completed our picket verandah. I love it!! 









Flooring

We had our flooring done by Choices flooring at Kotara. They were so easy to deal with and did an excellent job! 







Finally...

On 10 June 2016 we finally had our keys handed to us by MJH. 20 months after we initially decided to build with them. 










Friday, 22 January 2016

Monday, 4 January 2016

Slab, frame and roof

Slab: 


Frame: 
Looking into the front hallway

Home theatre

Kitchen 

Laundry

Jay tested the bath out! 

Panoramic view from the front verandah.

Roof:













Friday, 4 December 2015

Retaining walls, excavation and piping...

With mum and dads help we completed the retaining walls and handed the block back to the builders. Not a bad job if I do say so myself! 

The builders then needed to fill the block with 335mm as they had initially cut it wrong! 

This week saw the piping completed and getting ready for the slab to be poured. 

Though I'm guessing this wasn't supposed to happen... 

Next we will see the slab being poured and the frame up by Christmas...