Trying to keep people up to date with our build is nearly impossible. Hopefully this blog might make things a little easier...
Friday, 4 December 2015
Retaining walls, excavation and piping...
With mum and dads help we completed the retaining walls and handed the block back to the builders. Not a bad job if I do say so myself!
Monday, 16 November 2015
Retaining continues...
Went back to the block today to continue with our retaining walls, only to find out post holes filled with water from the recent rain.
Saturday, 14 November 2015
Starting the retaining walls
Today we started our retaining walls by digging 12 x 1.2m holes in order to stand a 2.4m post in it. Thank god for dingos!!! Too bad about the weather! 12 holes to go!
We hit quite a bit of rock which delayed us, however on average we got one hole every 15-20 mins. Unfortunately we had a set back with thunder storms and rain this morning, hopefully tomorrow will be better.
Monday, 9 November 2015
Fill Removal
Sunday, 1 November 2015
Excavations
It took almost 6 months to get through council and we had a lot of issues, however at the end of August we finally got notification that it was complete.
Our block was pegged out on the 16th of September, with excavations supposed to begin the following week. Issues occurred whereby our 'lovely' neighbors had placed their bricks and sand on our block, which delayed our excavations by a week - like we needed any more delays.
Excavations occurred on Friday the 23rd of September, and the approx 175 tonne of fill to be removed was actually found to be around 750 tonne. This means our removal cost climbs from $1100 to $15000. A huge difference, and some more unwelcome delays.
The site has been handed back to us for the removal of fill, and construction of retaining walls. These were supposed to be 20m on the left side and 27m on the right side. We marked it all out over the weekend and from what we can tell it should be 16m on the left, and 12.5m on the right. A large difference to what MJH had in the contract.
Wednesday, 20 May 2015
Waiting for council
Well, we have now completed our electrical selections, and have signed off on our loan paperwork with NAB. Now all we need is for council to approve everything. It has been with them since 10 April 2015 and we're still waiting. Today they came back to identify 'missing' parts of the application, all of which was already given to them. Due to these requirements they have changed our predicted date of approval to sometime in July. What a joke. Hopefully Lake Macquarie surprise us and approve it all earlier than that. Unfortunately, what they don't realize, is that we will be missing out on a number of financial benefits if they with hold out approval for that long!
Oh well, time will tell.
Monday, 2 March 2015
Selections day
Today we did our selections. This is what we came up with:
Roof - colour bond 'monument'
Fascias and gutters - colour bond 'surf mist'
External doors, windows and eaves - 'surf mist'
Garage - 'monument' ranch style
Bathroom windows - clear glass to be dressed with plantation shutters in white
Front door - Hume nex 35 with clear glass
Stainless flyscreens to all windows
Doors - diamond safety screen to sliding
External - governor handles with dead locks
Internal:
Doors - Hume alpine doors
Bathrooms & laundry
300x300 solar Nero 30 floor tiles
300x600 solar Nero wall tiles
Ceasarstone ice snow bench
Polytec char oak vanity
Kitchen
1 bin drawer
Ceasarstone 20mm benchtop
Classic white matte cabinets
Splash back - handcrafted 'manual marina' 75x150 tile
Smug appliances including 900mm freestanding oven/cooktop
Ducted range hood
Paint
Taubmans 'marble mist' - walls
Taubmans 'illusive white' architraves, skirting & cornices
Flooring
Gerfloor creation clic 'wild oak' to all living areas, kitchen and halls
Red book 'elsden' midnight to all bedrooms and home theatre
Tuesday, 10 February 2015
Consolidated tender
We finally received our consolidated tender, bush fire report, soil report and siting. We were glad to find no surprises so signed off on it.
Now we wait for our plans to be drawn up (meeting on the 23rd Feb), and our colour selections (3rd of March)... Then we will finally be underway!
Subscribe to:
Posts (Atom)